Report board meeting 20260224 teleconf: Difference between revisions

Jump to navigation Jump to search
m
Tag: 2017 source edit
Tag: 2017 source edit
Line 37: Line 37:
   - Waiting for the final report of the dry run result, fixes of requested changes to do have already started is on going
   - Waiting for the final report of the dry run result, fixes of requested changes to do have already started is on going
   - Dev remains to do and are planned for v24.
   - Dev remains to do and are planned for v24.
   - Real final certification: Date should be defined after the dry run. We hope April 2026.
   - Real final certification: Date should be defined after the dry run. We hope June 2026.


As new French budget-law 2026 was voted the 2 of February 2026, the auto attestation will be available again
As new French budget-law 2026 was voted the 2 of February 2026, the auto attestation will be available again